* 23.25km Ikot-Ekaide,Ikot-Okoro-Ikot -Ibiritam Road with 2-bridges.
* Inherited by Gov Umo Eno in 2023 at only 50% completion.

β Bridge One is 20m span with two abutments on a pile foundation each sitting on a 10-piles of 800milimeters diameter and 27-meters depth.
β The 80m Bridge Two carries a 4-spans of 20m, two abutments and 3-piers.
βBridges to have first maintenance only after 50years
β A 10.3m single carriageway of 8m width and 1.15m walkway/shoulder on both sides

β Road constructed with flexible pavements
* 46km End-to-end drains of 0.9m by 0.9m
*Situates with the ARISE Agenda praxis of Agriculture, Rural Development and Infrastructural Maintenance
* Shorter route to Rivers State via East West Road
* β 12.5km Road / Bridges, handled by AMITEC while the second section 10.75km is handled by NSIK ENGINEERING
* β Inherited at 50% execution from the immediate past government